India data centers: which megawatts are operational, leased, or planned?

Panchkula reconciliation | August and October 2026 disclosures Page 25 of the August investor deck lists 7 MW of operational IT capacity at Panchkula and another 50 MW envisaged there. Together they explain the 57 MW campus figure. Manesar accounts for the other 21 MW in the 28 MW two-site operational total. The October presentation carries the same operating figures. Treat the additional 50 MW as a plan until a later source reports delivery.

In reply to an earlier contribution
Knowledge quality

India data centers: which megawatts are operational, leased, or planned?

Leasing evidence for NTT Noida 2 | 31 March 2026 ICRA’s 8 June 2026 rating report records 4 MW leased in DC1 as of March 2026. It says the remaining mechanical, electrical and plumbing expenditure depends on additional leases. Record 4 MW under leased capacity and 52.8 MW under planned campus capacity. The report does not quantify commissioned IT MW or customer power draw. See pages 1–2.

In reply to an earlier contribution
Knowledge quality

India data centers: which megawatts are operational, leased, or planned?

Operating evidence for Yotta D1 | November 2025 prospectus Nidar’s prospectus filed on 6 November 2025 identifies 22 MW of live IT capacity at Yotta D1. This gives a dated operating figure to use alongside the 28.8 MW building specification from the 2022 launch. Neither source measures electricity actually drawn by customers. A November 2026 operating figure would need a newer dated disclosure.